On Friday,August 11, 2017, crews will begin mobilization of equipment and preparation work. Typical hours of work are 7:00AM - 6:00PM. Residents and business owners who need to drive after application begins,should park on unaffected side streets. Access to your street and/or drive may be interrupted for one day up to 8-10 hours. SLURRY SEAL 2017

The contractor sweeps sand from streets one and three weeks after entire application. The duration of the project is approximately three (3) days (which of course depends on cooperation of our local weather and any unforeseen construction conditions). Slurry Seal on these streets (road closed except for emergencies)

Monday 14 August 07:00…17:00
Marine Heights Way
Carol Ann Court
Owen Lane
Ellisport Place
Castilleja Place
Coralroot Place
Shannon Point Road

Tuesday 15 August 07:00…17:00
Washington Boulevard
Anaco Beach Place
Osprey Lane
Marine Crest Drive

Contact: Gunnar Christiansen, Project Manager gunnarc@cityofanacortes.org  360. 661.3708 or
Tim Hohmann (360) 588-8068 timh@cityofanacortes.org